November 25, 2026
High-voltage transmission tower and power lines against a blue sky

Photo: Ron Clausen via Wikimedia Commons. CC0 public domain dedication. Illustrative image of electric transmission lines.

Irving-based Vistra earned $1.14 billion in Q3 2026 as its Texas plants drove a 50% jump in adjusted EBITDA. Guidance, Comanche Peak and data-center deals.

Quick Answer: Irving-based Vistra reported third-quarter 2026 net income of $1.14 billion, up from $652 million a year earlier, and Ongoing Operations Adjusted EBITDA of $2.378 billion, up about 50%. Its Texas generation segment produced $1.227 billion of that total, more than half. The company narrowed its 2026 guidance to $7.1 billion to $7.5 billion, opened 2027 guidance at $7.7 billion to $8.5 billion, and closed a 5,500-megawatt natural gas acquisition on October 30.

Vistra released the results on November 6, 2026, covering the three months ended September 30, 2026. The figures below come from that release and the company’s Form 10-Q; percentages are calculated from the reported figures.

What did Vistra report for the third quarter of 2026?

Operating revenues were $6.347 billion, compared with $4.971 billion in the third quarter of 2025, an increase of about 28%. Net income rose by $488 million to $1.14 billion.

The company’s preferred operating measure, Ongoing Operations Adjusted EBITDA, rose by $797 million to $2.378 billion from $1.581 billion. Vistra attributed the increase to higher realized energy and capacity prices, a full three months of contribution from the natural gas plants it bought from Lotus in October 2025, and the return of Martin Lake Unit 1 in East Texas to operating status.

The net income figure needs one caution. It includes a $559 million unrealized gain on hedging positions, a non-cash item that moves with forward power and gas prices. It also absorbs a $269 million impairment tied to the 350-megawatt Moss Landing battery facility in California.

Measure Q3 2026 Q3 2025 Nine months 2026 Nine months 2025
Operating revenues $6,347 million $4,971 million $16,004 million Not shown
Net income $1,140 million $652 million $2,474 million $711 million
Ongoing Operations Adjusted EBITDA $2,378 million $1,581 million $5,639 million $4,170 million

How much of Vistra’s earnings come from Texas?

Vistra reports four operating segments: Retail, Texas, East and West. The Texas segment, which holds the company’s power plants in the Electric Reliability Council of Texas (ERCOT) market, generated $1.227 billion of Adjusted EBITDA in the quarter, up from $784 million, an increase of about 57%. That is roughly 52% of the company’s Ongoing Operations total. For the first nine months of 2026, Texas produced $2.124 billion, up from $1.416 billion.

Segment Adjusted EBITDA Q3 2026 Q3 2025 Nine months 2026 Nine months 2025
Texas $1,227 million $784 million $2,124 million $1,416 million
East $979 million $719 million $2,422 million $1,651 million
Retail $98 million $37 million $939 million $977 million
West $76 million $63 million $200 million $174 million
Ongoing Operations total (after corporate items) $2,378 million $1,581 million $5,639 million $4,170 million

How hard did the Texas plants run?

The 10-Q shows the Texas fleet generated more power from every fuel type than a year earlier. Natural gas plants produced 16,499 gigawatt-hours in the quarter, up from 15,455. Lignite and coal units produced 7,735 gigawatt-hours, up from 6,223. Nuclear output was 5,198 gigawatt-hours, up from 5,028, and solar was 349 gigawatt-hours, up from 212. Combined output was roughly 11% higher than in the third quarter of 2025.

Capacity factors rose as well. Texas combined-cycle gas plants ran at 81.7%, compared with 73.7% a year earlier. Lignite and coal units ran at 72.7%, up from 58.5%, a change that reflects in part the return of the 815-megawatt Martin Lake Unit 1. That unit, damaged by a fire in November 2024, returned to service in February 2026. The Texas nuclear capacity factor was 98.1%, up from 94.9%.

What is Comanche Peak’s role, and what is the Amazon deal?

Comanche Peak, in Glen Rose in Somervell County southwest of Fort Worth, is Vistra’s only nuclear plant in Texas and the sole source of the Texas segment’s nuclear generation. The two-unit plant has a capacity of 2,400 megawatts. In July 2024 the Nuclear Regulatory Commission approved a 20-year license extension that allows Unit 1 to operate through 2050 and Unit 2 through 2053. A company fact sheet updated in October 2025 listed 679 employees at the site.

Half of the plant’s output is now committed to a single customer. According to the 10-Q, Vistra signed a power purchase agreement with Amazon Web Services in September 2025 for 1,200 megawatts of carbon-free power from Comanche Peak. The term is 20 years, with options to extend for up to 20 more. Deliveries are scheduled to begin in the fourth quarter of 2027 and ramp to the full amount by 2032.

That timing matters for reading the guidance. The Amazon contract contributes nothing to 2026 results and only a first quarter of initial deliveries falls inside the 2027 guidance year. The remaining 1,200 megawatts at Comanche Peak is not covered by an announced long-term contract.

What other data-center power deals has Vistra signed?

The newest Texas agreement is in the Permian Basin, not North Texas. On September 21, 2026, New Era Energy & Digital announced a 20-year power purchase agreement with Luminant ET Services, a Vistra affiliate, for a minimum of 200 megawatts and up to 207 megawatts. The power will come from Vistra’s natural gas plant in Odessa and will serve the first phase of the Texas Critical Data Centers campus, a 493-acre site next to the plant. New Era said firm power is expected to be available in the third quarter of 2027. A companion agreement gives Vistra a 5% non-voting interest in the portion of the project it powers once deliveries start.

Outside Texas, the 10-Q describes 20-year agreements with Meta signed in January 2026 totaling 2,609 megawatts from three nuclear plants in the PJM market. They cover 1,268 megawatts of operating output at Perry and 908 megawatts at Davis-Besse, plus planned capacity increases at those plants and at Beaver Valley. Deliveries from operating capacity begin in late 2026. The 405-megawatt Pulaski Solar Facility in Illinois also began operating under a contract with Microsoft.

How did TXU Energy and the retail business perform?

Vistra’s retail segment sells electricity under brands that include TXU Energy, its flagship Texas brand, along with 4Change Energy, TriEagle Energy and Ambit Energy. The company does not break out TXU Energy’s results separately. The segment as a whole earned $98 million of Adjusted EBITDA in the third quarter, up from $37 million, which Vistra tied in part to higher contractual rates.

The nine-month picture is weaker. Retail Adjusted EBITDA was $939 million, down from $977 million. The filing cites lower margins from excess volumes that had to be sold at lower wholesale prices. On a net income basis, the retail segment lost $103 million over nine months because of a $1.097 billion swing in unrealized hedging losses.

Texas remains the core of the retail book. Of the 38,424 gigawatt-hours of retail electricity Vistra sold in the quarter, 23,300 gigawatt-hours, or about 61%, were sold in ERCOT.

What guidance did Vistra give for 2026 and 2027?

The company narrowed its 2026 range for Ongoing Operations Adjusted EBITDA to $7.1 billion to $7.5 billion and said the midpoint moved higher. Through nine months it had earned $5.639 billion, about 77% of the $7.3 billion midpoint. It also introduced 2027 guidance of $7.7 billion to $8.5 billion, a midpoint of $8.1 billion.

Guidance measure 2026 (narrowed) 2027 (initiated)
Ongoing Operations Adjusted EBITDA $7.1 billion to $7.5 billion $7.7 billion to $8.5 billion
Ongoing Operations Adjusted free cash flow before growth $4.3 billion to $4.7 billion $4.3 billion to $5.1 billion

Hedging explains why the company can give a range a year ahead. As of October 30, Vistra had sold forward about 98% of the power it expects to generate in 2027 and about 78% for 2028. The 2028 position is the more exposed one. An Earnings Whispers review of the November 6 earnings call reported that management trimmed its ERCOT load-growth outlook through 2030 to a range of 4% to 6% and acknowledged slower near-term connection of large new loads in Texas.

How is Vistra expanding its generation fleet?

On October 30, 2026, after the quarter closed, Vistra completed its purchase of Cogentrix Energy from funds managed by Quantum Capital Group. The deal added 10 natural gas plants with about 5,500 megawatts of capacity and brought the company’s fleet to nearly 50,000 megawatts. Nine of the plants are in the PJM and New England markets. The tenth is in Texas: Altura Cogeneration, a 583-megawatt facility in ERCOT.

The 10-Q puts the consideration at about $2.2 billion in cash, the assumption of $1.7 billion of Cogentrix debt, and 5 million Vistra shares valued at $185 each, or $925 million. Vistra repaid the assumed debt on November 5.

What is Vistra building in Texas?

The filing restates a plan first announced in May 2024 to add up to 2,000 megawatts of gas-fueled capacity in Texas. It has three parts:

  • Up to 860 megawatts of simple-cycle peaking units in West Texas, expected online in 2028. A subsidiary, Permian Power, secured a $583 million loan from the Texas Energy Fund in June 2026 at a fixed 3.0% rate; $236 million was outstanding at September 30.
  • Conversion of the Coleto Creek plant near Goliad from coal to natural gas, at up to 600 megawatts. The coal unit retired in September 2026.
  • Upgrades at existing gas plants adding more than 500 megawatts of summer capacity and 100 megawatts of winter capacity.

What does Vistra’s balance sheet look like after the quarter?

Vistra ended September with about $8.923 billion of available liquidity, including $2.743 billion of cash. That cushion was built ahead of known uses. In October and November the company paid for Cogentrix, repaid the assumed debt and redeemed all $1 billion of its Series A preferred stock, leaving pro forma liquidity of about $5.4 billion.

Shareholder returns continued. Vistra spent $917 million on share repurchases in the first nine months of 2026 and paid $231 million in common dividends. It has bought back about $6.7 billion of stock since November 2021, leaving about 339 million shares outstanding, roughly 30% fewer than when the program began. The board added $1.5 billion to the authorization, bringing the remaining amount to about $2.5 billion, which the company expects to use by the end of 2028.

How large is Vistra’s footprint in Dallas-Fort Worth?

Company snapshot Detail
Headquarters 6555 Sierra Drive, Irving, Texas
Irving employees (October 2025 fact sheet) 1,167 at headquarters; 782 at the Royal Lane building
Texas employees and facilities (October 2025) About 4,000 employees; 26 facilities
Retail customers (October 2025) About 5 million companywide
Generation capacity Nearly 50,000 MW after Cogentrix closing
Largest North Texas plants (October 2025) Comanche Peak 2,400 MW; Forney 1,912 MW; Midlothian 1,596 MW; Lake Hubbard in Sunnyvale 921 MW

Brian’s Take

I’m Brian French, and as a former investment manager and analyst the first thing I do with a report like this is separate cash-like earnings from accounting noise. The $1.14 billion of net income includes a $559 million unrealized hedging gain, and the same line item cut the other way for the retail segment over nine months. The cleaner signal to me is the Texas segment: $1.227 billion of Adjusted EBITDA in one quarter, with gas, coal and nuclear units all running harder than a year ago.

What I find most telling for Texas business is how the data-center story is actually arriving. The Amazon contract at Comanche Peak does not start until late 2027 and takes until 2032 to reach full size. The Odessa deal is 207 megawatts beginning in 2027. These are long ramps, not a switch being flipped, and half of Comanche Peak is still uncontracted.

I would also note where the growth capital went this year. Nine of the ten Cogentrix plants are outside Texas, and the East segment’s nine-month Adjusted EBITDA is already larger than Texas’s. Vistra is headquartered in Irving, but its earnings base is becoming steadily less Texan.

Frequently Asked Questions

How much did Vistra earn in the third quarter of 2026?

Vistra reported net income of $1.14 billion on operating revenues of $6.347 billion for the quarter ended September 30, 2026. Ongoing Operations Adjusted EBITDA was $2.378 billion, compared with $1.581 billion a year earlier.

What is Vistra’s guidance for 2027?

The company initiated 2027 guidance of $7.7 billion to $8.5 billion for Ongoing Operations Adjusted EBITDA and $4.3 billion to $5.1 billion for adjusted free cash flow before growth. It said about 98% of expected 2027 generation was hedged as of October 30, 2026.

Who buys power from Comanche Peak?

Amazon Web Services has a 20-year agreement for 1,200 megawatts from the 2,400-megawatt plant, with deliveries starting in the fourth quarter of 2027 and reaching the full amount by 2032.

Is TXU Energy part of Vistra?

Yes. TXU Energy is one of Vistra’s retail electricity brands. Vistra does not report TXU Energy’s results separately; the retail segment as a whole produced $98 million of Adjusted EBITDA in the third quarter and $939 million over the first nine months of 2026.

Sources and Further Reading

  1. Vistra Reports Third Quarter 2026 Results (earnings release, Form 8-K exhibit, November 6, 2026) — Vistra Corp. / U.S. Securities and Exchange Commission
  2. Form 10-Q for the quarter ended September 30, 2026 — Vistra Corp. / U.S. Securities and Exchange Commission
  3. Vistra Completes Acquisition of Cogentrix Energy (October 30, 2026) — Vistra Corp.
  4. New Era Energy & Digital Secures 20-Year 207 MW PPA with Vistra (September 21, 2026) — New Era Energy & Digital
  5. Vistra Receives Approval to Operate Comanche Peak Nuclear Plant Through 2053 (July 30, 2024) — Vistra Corp.
  6. Vistra in Texas fact sheet (updated October 2025) — Vistra Corp.
  7. Vistra third-quarter 2026 earnings review (November 9, 2026) — Earnings Whispers