Dallas now expects its convention center rebuild in 2030, not 2029. Here are the costs, contracts, financing and bookings behind the multibillion-dollar job.

Quick Answer: The rebuilt Kay Bailey Hutchison Convention Center Dallas is now expected in 2030, a year later than the 2029 target the city cited in early 2026. The Dallas City Council voted in June 2026 to keep the current design after staff estimated a proposed redesign would add about $597 million and another year. Demolition of three exhibit halls is under way, backed by a bridge loan of up to $1 billion.

Dallas closed its convention center in July 2025 to replace it with a larger building meant to compete for the country’s biggest trade shows. Sixteen months later, the project has a completed schematic design, a construction manager, a first guaranteed price, a financing zone that is collecting far more than forecast, and a delivery date that has moved back a year. This is where the numbers stand as of November 23, 2026, based on City of Dallas memos, releases and budget documents; the most recent city records reviewed for this article date from September 2026.

What is Dallas building?

The city’s plan calls for 750,000 square feet of contiguous exhibit hall space, 105,000 square feet of ballroom space and 180,000 square feet of meeting rooms, according to a City of Dallas project update from February 2026. Those three components alone come to just over 1 million square feet of sellable space. A 2024 report by CoStar News put the expanded center at 2.5 million square feet in total.

The plan is also a land deal. By reorienting the building, the city expects to free up more than 30 acres of developable land around the site on the southern edge of downtown. The City Plan Commission approved a replat of the site on November 20, 2025, covering a 63.182-acre tract divided into six lots.

The case for replacing rather than repairing the old building rests partly on its condition. Audits in 2018 and 2019 found about $600 million in deferred maintenance at the existing facility, according to a city reference memo on the project.

How much will the convention center cost?

There is no single agreed public figure, and readers should treat any total with caution. CoStar News described the project as a $3.7 billion revamp when the city held a ceremonial groundbreaking in late June 2024. NBC 5 and The Dallas Morning News put it at $3.8 billion in June 2026. The city documents reviewed for this article list individual contracts and financing limits rather than a single updated total.

How is the rebuild being paid for?

The project is funded by visitors rather than by property taxes. Dallas voters approved Proposition A in a special election on November 8, 2022, authorizing a 2% increase in the hotel occupancy tax for 30 years under a state law known as the Brimer Bill. The proceeds are split 80% to the convention center master plan and 20% to venue projects at Fair Park.

The second source is a Project Financing Zone, created October 13, 2021, which captures the growth in certain state hotel-related taxes within a 3-mile radius of the center for 30 years. The zone covers 84 distinct locations. By June 2026 it had collected $189,144,538, about three times early estimates, according to a city manager memo. In February 2026 the city said hotel occupancy tax and zone revenue for the project had together passed $224 million.

Against that revenue, the council has authorized a series of borrowings. It approved Series 2023 special tax revenue obligations of up to $172 million on September 27, 2023. On June 11, 2025, it approved a bridge loan in the form of senior lien special tax revenue notes of up to $1 billion, with JPMorgan Chase Bank as the lender through DNT Asset Trust. On January 28, 2026, it increased State Infrastructure Bank financing tied to the project by $26 million, from $90 million to $116 million. The city said in February that long-term revenue bonds were planned for 2026; the documents reviewed do not confirm whether those bonds have been sold.

The credit behind the plan has strengthened. Fitch upgraded the city’s hotel occupancy tax rating to AA from A+, according to an August 2024 city memo.

Financing and revenue item Amount Date
Hotel occupancy tax increase (Proposition A) 2% for 30 years Approved Nov. 8, 2022
Series 2023 special tax revenue obligations Up to $172 million Sept. 27, 2023
Bridge loan, senior lien notes Up to $1 billion June 11, 2025
State Infrastructure Bank financing $116 million, up from $90 million Jan. 28, 2026
Project Financing Zone collections $189.1 million As of June 2026
FY2026-27 transfer to capital construction fund Up to $55.5 million Effective Oct. 1, 2026

Source: City of Dallas project reference memo, city manager memorandum and FY2026-27 appropriations ordinance.

Who is building it, and what has been awarded?

The city has assembled the project team through a sequence of council votes. Inspire Dallas, a group led by Matthews Southwest, is the program manager and owner’s representative under a six-year contract approved September 13, 2023, worth $65 million plus a $2 million contingency. The design contract, with Perkins and Will and with Populous also on the team, was approved September 11, 2024, for no more than $141,502,525.

Trinity Alliance Ventures was approved as construction manager at risk on November 13, 2024, with a pre-construction fee capped at $7.55 million. The first guaranteed maximum price, approved June 11, 2025, the same day as the bridge loan, was set at no more than $249,979,369, including a contingency of about $14.1 million.

Other pieces fill in the picture. On April 23, 2025, the council authorized buying two tracts from Charter DMN Holdings: about 185,941 square feet for up to $45.12 million and about 36,228 square feet for up to $6.55 million, a combined 5.1 acres for as much as $51.7 million. An owner-controlled insurance program through Marsh USA, approved August 27, 2025, runs up to $58.76 million with coverage through August 27, 2030. An interlocal agreement with Dallas Area Rapid Transit, approved November 12, 2025, covers up to $3 million for its first 18 months.

Contract Firm Not to exceed
Program manager Inspire Dallas (Matthews Southwest) $65 million plus $2 million contingency
Design Perkins and Will, with Populous $141.5 million
Pre-construction, CM at risk Trinity Alliance Ventures $7.55 million
Guaranteed maximum price 1 Trinity Alliance Ventures $249.98 million
Owner-controlled insurance Marsh USA $58.76 million
Destination marketing, 2025 to 2028 Visit Dallas $46.2 million

Why did the completion date move to 2030?

The schedule held through the start of 2026. The existing facility closed in July 2025. The DART convention center station closed on January 5, 2026, and will stay closed for the duration of construction. City staff told the council on January 21, 2026, that schematic design was 100% complete. On February 25 the city announced that demolition of Halls D, E and F was under way while Halls A, B and C remained active, said major demolition should be substantially complete by the end of 2026, and gave 2029 as the completion target.

The delay came from a design dispute over roads on the Oak Cliff side of the site. On May 19, 2026, the council’s Transportation and Infrastructure Committee recommended a redesign. City staff responded with a memo estimating that the redesign would cost about $597 million, for which no funding had been identified, and add roughly a year. A June 16 memo said completion would slip into 2030.

Staff also put a price on waiting. The memo counted about $271.3 million in known losses from clients redirecting events, estimated about $1.4 million a month in lost revenue for further delay, and cited more than 6,000 tourism and hospitality jobs at risk. As an alternative to redesigning the building, staff offered a package of roadway improvements with a conceptual estimate of $97.3 million.

What did the City Council decide?

On June 24, 2026, the council voted against the redesign. The Dallas Observer reported the vote as 9 to 6. The city said the next day that the council had directed staff to advance the current design and to hire an independent transportation consultant. Delivery is now expected in 2030. NBC 5 and The Dallas Morning News reported that nine conventions would have to relocate because of the latest delay.

What has the closure cost Dallas so far?

Closing a convention center for years has a direct price. Visit Dallas said the city had lost $92 million in convention lodging business and $13 million in taxes since the closure, according to a CBS News Texas report in June 2026. Those figures are separate from the staff estimate of $271.3 million in redirected client business tied to the schedule.

The building was not empty during that period. Under an agreement the council approved on December 11, 2024, FIFA used the center for eight months in 2026, with city spending capped at $15 million, and it served as the International Broadcast Center for the 2026 World Cup through August.

What is booked for the new building?

The sales effort has continued through construction. In February 2026 the city said 70 major conventions were booked for 2029 and beyond, worth $1.9 billion in total economic impact. In June, Visit Dallas described a pipeline for 2031 and beyond worth more than $4.5 billion in potential economic impact. An earlier count, from 2024, showed 43 conventions booked for the new center worth more than $1 billion. Those three figures were measured at different times and on different bases, so they should not be read as a trend line.

The city also renewed its contract with Visit Dallas, the organization that sells the building, for October 1, 2025, through September 30, 2028, at a cost of up to $46,209,045.

What does the new city budget set aside?

The fiscal 2026-27 budget, which took effect October 1, 2026, keeps money moving to the project. The appropriations ordinance sets the Convention and Event Services appropriation at $129,681,569. It authorizes a transfer of up to $55,480,861 to the Convention Center Capital Construction Fund and up to $19,400,819 for debt service on Series 2021 hotel occupancy tax refunding bonds. The version reviewed for this article was the ordinance prepared for the council’s second reading on September 16, 2026.

Key fact Detail
Exhibit hall space 750,000 square feet, contiguous
Ballroom and meeting space 105,000 and 180,000 square feet
Developable land freed More than 30 acres
Old center closed July 2025
Demolition Halls D, E and F, announced Feb. 25, 2026
Rejected redesign About $597 million, about one more year
Expected delivery 2030, previously 2029

What should Dallas businesses watch next?

Four items will show whether 2030 holds. The first is demolition, which the city expected to be substantially complete by the end of 2026. The second is the long-term bond sale that would replace the bridge loan. The third is the next guaranteed maximum price, since the first one covers only about $250 million of work. The fourth is the independent transportation review the council ordered in June, which was the issue that put the schedule at risk in the first place.

For downtown hotels, restaurants and event suppliers, the arithmetic is plain. City staff valued each month of delay at about $1.4 million in lost revenue, and Visit Dallas has already tallied $92 million in lost convention lodging. The bookings for 2029 and later are the other side of that ledger, and their value depends on the building opening when the city now says it will.

Frequently Asked Questions

When will the new Dallas convention center open?

The City of Dallas now expects delivery in 2030. As recently as February 2026 the target was 2029.

How is the Dallas convention center rebuild funded?

Primarily through a 2% hotel occupancy tax increase approved by voters as Proposition A in November 2022 and a Project Financing Zone created in 2021. The zone had collected $189.1 million by June 2026. The council has also approved a bridge loan of up to $1 billion.

How big will the new convention center be?

Plans call for 750,000 square feet of contiguous exhibit space, 105,000 square feet of ballroom space and 180,000 square feet of meeting rooms.

Why was the project delayed?

A council committee recommended a redesign in May 2026 over roadway concerns. Staff estimated the redesign at about $597 million and one more year. The council rejected it on June 24, 2026, but the schedule had already moved to 2030.

Who is building the Dallas convention center?

Inspire Dallas, led by Matthews Southwest, is program manager. Perkins and Will leads design with Populous, and Trinity Alliance Ventures is the construction manager at risk.

Is the DART convention center station open?

No. The station closed January 5, 2026, and is to remain closed for the duration of construction.

Sources and Further Reading

  1. KBHCCD Master Plan Component 1 Reference Tool memorandum, February 12, 2026, City of Dallas
  2. Memorandum: Viaduct Recommendation Impact, June 18, 2026, City of Dallas City Manager
  3. Major Demolition Underway at Kay Bailey Hutchison Convention Center Dallas, City of Dallas
  4. Dallas City Council Keeps Convention Center Redevelopment on Track, City of Dallas
  5. City of Dallas Marks Progress on Convention Center Expansion, City of Dallas
  6. FY 2026-27 Operating and Capital Budgets Appropriations Ordinance, City of Dallas
  7. Dallas convention center delayed until 2030, NBC 5 Dallas-Fort Worth and The Dallas Morning News
  8. Concerns linger as convention center redesign shot down by Dallas City Council, Dallas Observer
  9. One of nation’s largest convention centers starts $3.7 billion revamp, CoStar News
  10. Kay Bailey Hutchison Convention Center Dallas construction and Oak Cliff viaduct report, CBS News Texas